Pharmaceutical · BESS
500 kWh Battery for Pharmaceutical Plant
An LFP containerized BESS reduced billed maximum demand and provided engineered backup for selected utilities without compromising site EHS protocols.
Project size
500 kWh / 250 kW PCS
Annual savings
₹42,00,000
Demand reduction
180 kVA
Annual ROI
18%
Payback
5.2 years
Location
Pune, Maharashtra
Load profile
Daytime HVAC-heavy with short utility peaks; critical clean-utility backup window of 1.5 hours.
Performance metrics
Cycles / year
~320
RTE (system)
92%
Solar paired
750 kWp
DG runtime cut
28%
- • Peak shaving + solar self-consumption modes
- • SCADA integrated with plant energy desk
- • Fire detection and HVAC packaged in container